Operations CXO Status Report

Friday 6 March 2020 9.00am EST

During the last week Chandra completed the observing schedule as planned.

A real-time procedure was executed on Mar 4 to perform a routine diagnostic dump of the Control Processing Electronics (CPE). Another real-time procedure was executed on Mar 4 to perform a routine self-check of the Electrical Interface Assembly (EIA) Sequencer.

The schedule of targets for the next week is shown below and includes an observation of GW170817 coordinated with VLA and HST, and an observation of SN2020oi, which is a follow-up to a Director's Discretionary Time Target of Opportunity which was accepted on Jan 21.



------------------------------------------
        Radiation Belts                     Mar  8
        M87Halo1               ACIS-S
        H1821+643              HRC-S /LETG  Mar  9
        A1240                  ACIS-I
        GW170817               ACIS-S
        E0102-72               ACIS-S       Mar 10
        SPT-CLJ2320-5233       ACIS-I
        Radiation Belts                     Mar 11
        SPT-CLJ0217-5014       ACIS-I
        Spiderweb              ACIS-S       Mar 12
        SN2020oi               ACIS-S
        H1821+643              HRC-S /LETG
        A1240                  ACIS-I       Mar 13
        GW170817               ACIS-S
        Radiation Belts                     Mar 14
        SPT-CLJ2323-5753       ACIS-I
        Spiderweb              ACIS-S
        GW170817               ACIS-S       Mar 15
        SPT-CLJ2334-5308       ACIS-I
        GW170817               ACIS-S
        Radiation Belts                     Mar 16

------------------------------------------

All spacecraft subsystems continued to support nominal operations.