Operations CXO Status Report

Friday 19 May 2006 9.00am EDT

During the last week Chandra completed the observing schedule as planned.

A realtime procedure was completed on May 12 to update the on-board Ephemeris.

The schedule of targets for next week is shown below and includes a series of observations of the coment 3P/Schwassmann-Wachmann.

------------------------------------------
G330.2+1.0              ACIS-I       May 21
XTE J1817-330           ACIS-S/HETG  May 22
3P/Schwassmann (5 obs)  ACIS-S       May 23
1RXS J212746.7+565      ACIS-S
NGC 6689                ACIS-S
Radiation Belts
GRB060605               ACIS-S       May 24
CXOPTM J181912.4-2      ACIS-I
RX J0806.3+1527         HRC-S/LETG   May 25
XTE J1726-283           HRC-I
M31                     ACIS-I
Radiation Belts                      May 26
AS 310                  ACIS-S
Q2237+0305              ACIS-S       May 27
PSR B1821-24            HRC-S
ELAIS-S1 C              ACIS-I
G284.0-0.9              ACIS-I
SDSSJ1301-0058          ACIS-S       May 28
SDSS J1733+5400         ACIS-S
UGC 11466               ACIS-S
PSR B1929+10            ACIS-S

------------------------------------------

All spacecraft subsystems continued to support nominal operations.