Operations CXO Status Report

Friday 18 June 2004 9:00am EDT

During the last week Chandra completed the observing schedule as planned.

A real-time procedure was completed on June 11 to update the on-board ephemeris.

The Cycle 6 Peer Review was held in Boston this past week.

The observing schedule for next week is shown below and includes coordinated observations of SGR 1806-20 with RXTE and PG 1211+143 with XMM-Newton:

------------------------------------------
PG 1211+143             ACIS-S/LETG  Jun 20 
2326-477                ACIS-S       Jun 21 
LBQS 2116-4439          ACIS-S
Radiation Belts
SGR 1806-20             ACIS-S       Jun 22 
MACS1115.2+5320         ACIS-I
PG 1211+143             ACIS-SLETG
M87                     ACIS-S       Jun 23 
NGC 2276                ACIS-S
0234+285                ACIS-S       Jun 24 
Radiation Belts
4U1755-33               ACIS-S       Jun 25 
PG 1211+143             ACIS-SLETG
XTE J1751-305           ACIS-S       Jun 26 
G344.7-0.1              ACIS-S
Radiation Belts                      Jun 27
SCULPTOR DWARF SPH      ACIS-S

------------------------------------------

All spacecraft subsystems continued to support nominal operations.