Friday 14 February 2003 8.30am EST
| During the last week Chandra completed the observing schedule as planned.
Chandra passed through the seventh and eighth eclipses of the Spring 2003 season on 8 and 11 of Feb with nominal power and thermal performance. Real-time procedures were run following each eclipse to disable the Momentum Unload subfunction in the flight software to ensure momentum dumps remain under manual control. A procedure to clear a glitch counter that incremented during eclipse exit was also run on 11 Feb. A real-time procedure was completed on Feb 12 to update the on-board ephemeris. The observing schedule for next week is shown below and includes a series of Calibration observations of AR Lac with the HRC. |
------------------------------------------
SDSS J104230.14+010223 ACIS-S Feb 17 NGC 4361 ACIS-S HS 1251+2636 ACIS-S GEV J1825-1310 ACIS-I MACHO-96-BLG-5 ACIS-S SGR 1900+14 ACIS-S RX J1914.4+2456 ACIS-S Feb 18 Radiation Belts RX J1914.4+2456 ACIS-S Feb 19 NGC 6888 ACIS-S Markarian 231 ACIS-S Feb 20 Radiation Belts Feb 21 ARLac (21 obs) HRC-S ARLac (21 obs) HRC-I Feb 22 NGC 315 ACIS-S 87GB 0718+2748 ACIS-S Feb 23 MACSJ-0911.2+1746 ACIS-I SDSS J015650.28+005308 ACIS-S RX J2217.9-5941 ACIS-S V838 Mon ACIS-S
------------------------------------------
All spacecraft subsystems, with the exception of MUPS thruster A-1 as noted above, continued to operate nominally.
Return to Status Reports